Water Supply Cross Connection, New Boston, AFS

The New Boston Air Force Station (NBAFS) water supply system did not provide adequate capacity for demand use including fire protection. As a subconsultant to a federal prime contractor, AECm provided construction management services for a new cross-connection system.

The project involved modification of the existing water supply infrastructure including new piping systems. Work included cleaning, disinfection, and recommissioning of two existing below grade storage tanks. The project was completed on a constrained schedule to mitigate impacts to critical facility operations.